A typical task status detail page might look like this.
A single post-processing task will often contain several individual steps. In this case, the task contains steps for Clipping, file Tagging, Adding the clip to the Library, ShowSqueezing the file, a Cloud Share, and Deleting the transcoded file. The steps are run in sequence, and the information on this page will reflect that- in this case, the Tag File and Add to Library steps will not show any progress until after the ShowSqueeze step is complete.
Click More Information for even more details.
The information on this page includes the following for each step of the task list:
•
Task name
•
Priority: this corresponds to the options on the Local Settings page, in the Admin section.
•
State: this can read Started, Idle, or Failed.
•
Status: This will show Complete or a failure message. Until the task is complete, this field will be blank.
•
Progress: percent of the step that has been completed
•
Executing machine: the name of the SnapStream node that is performing this step
•
Time Created: the time at which the task was submitted
•
Time Completed: the time at which this step was completed
•
Source Machine: the name of the SnapStream node on which the recording is located
•
Source File: the path and filename of the recording
•
Destination Machine: the name of the SnapStream node on which the recording will be located after the completion of this step
•
Run Count: the number of times this step has been run. This will increment if the task fails and restarts.
•
Run Immediate: Indicates a Time-Constrained task that is set to ignore time constraints. For information on task categories, see the Local Settings page, in the Admin section
•
User ID: The user who created the task, if it was submitted manually.
•
Task ID: The unique identifier for the Task
•
Additional diagnostic information about the task, which changes depending on the type of task
Example 1: Clip
A Clip task will show the Title, Start and End points (in both clock time and elapsed time), and Duration
Example 2: ShowSqueeze
A transcoding task will show the the Format and the Profile name that were used.
Example 3: Share Clip
A clip share task will show the To address, the From address, and the Subject of the email that was sent.